Problem 12-09 (Algorithmic)
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity

Activity Time(weeks)

Probability
A

3

0.29

4

0.38

5

0.29

6

0.04

B

7

0.22

9

0.53

11

0.25

C

9

0.05

11

0.24

13

0.36

15

0.19

17

0.16

D

10

0.59

12

0.41

Provide the base-case, worst-case, and best-case calculations for the time to complete the project.Activity
Base case
Worst case
Best case
A
weeks
weeks
weeks
B
weeks
weeks
weeks
C
weeks
weeks
weeks
D
weeks
weeks
weeks
Total
weeks
weeks
weeks
Note that the answer for base case in part A were wrong. I only need the answer for base case. Thank you!
a. Provide the base-case, worst-case, and best-case calculations f the time to com Activity Base case Worst case Best case weeks weeks 4.08 W ks A 3 weeks weeks 06 11 weeks 7 weeks weeks 13.3 weeks 17 9 C Weeks weeks weeks 1.82 12 10 weeks weeks weeks Total 46 29 37.3. Get Finance homework help today
TOP ACADEMIC WRITER
He has decades of experience in the education field and has served in the examination boards of some of the top Universities within & outside the United States America.

Related

Algorithmic Assignment | Homework For You |

 

Homework Nerds have been helping students since 2006. Contact us today, and let us take care of all your academic needs. At Homework Nerds, we can take care of your academic needs. We can write your papers, do your presentations, learning team assignments, Labs, discussion questions and final exams. We also offer an entire week and entire class plans where we login to your classroom and take care of all class activities for you.

Homework Nerds: The #1 Most trusted academic services website.

CLICK HERE TO ORDER NOW 

Algorithmic Assignment | Homework For You |

Problem 12-09 (Algorithmic)
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity

Activity Time(weeks)

Probability
A

3

0.29

4

0.38

5

0.29

6

0.04

B

7

0.22

9

0.53

11

0.25

C

9

0.05

11

0.24

13

0.36

15

0.19

17

0.16

D

10

0.59

12

0.41

Provide the base-case, worst-case, and best-case calculations for the time to complete the project.Activity
Base case
Worst case
Best case
A
weeks
weeks
weeks
B
weeks
weeks
weeks
C
weeks
weeks
weeks
D
weeks
weeks
weeks
Total
weeks
weeks
weeks
Note that the answer for base case in part A were wrong. I only need the answer for base case. Thank you!
a. Provide the base-case, worst-case, and best-case calculations f the time to com Activity Base case Worst case Best case weeks weeks 4.08 W ks A 3 weeks weeks 06 11 weeks 7 weeks weeks 13.3 weeks 17 9 C Weeks weeks weeks 1.82 12 10 weeks weeks weeks Total 46 29 37.3. Get Finance homework help today